PHOTO
The Transmission Company of Nigeria (TCN) has said that the 330kV Akure Transmission Substation in Ondo State, which is at 98 per cent completion, will be completed in five months.
This was even as it said efforts were being made to complete the 330kV transmission line that would supply power to the substation.
The Executive Director, Transmission Service Provider, TCN, Engr. Victor Adewumi made the disclosure during the on-the-spot assessment of the facility at the instance of the Minister of Power, Engr. Abubakar Aliyu.
The Akure 330/132/33kV Substation he said, has two units of 150MVA transformer on the 330kV section, four outgoing 132kV line bays, and two units of 60MVA on the 132kV side with four outgoing feeder bays as well as six outgoing feeder bays on the 33kV side, to enable Benin DisCo offtake electricity for its consumers.
According to Engr. Adewumi, on completion, the substation can deliver up to 96MW of electricity to the good people of Ondo State and Ekiti State from the 2 units 60MVA, 132/33kV transformers.
He noted that the completion of the 330kV transmission line was hindered by Right of Way (RoW) issues, most of which have been resolved by the intervention of the Osun, Ekiti and Ondo State governors.
The substation, he explained, would receive supply from two 330kV lines, the Osogbo – Akure line and the Akure-Ihovbor line.
“This will ensure the power source meets the N-1 criteria, such that if there is a problem on one line the station will still receive bulk power supply from the other alternative healthy line,” he said.
He added that the Akure Substation “is one of the projects the Minister of Power classified as a priority project that he wants to commission before the end of this year.
“The project is ready and we are hoping that in five months, the lines will be completed and the Minister will commission this substation”.
The ED further noted that the line that was originally designed for the substation which is the 330KV Double Circuit from Osogbo to Ihovbor with a turn in and out at Akure might not be completed in five months because of the distance of the line and the number of outstanding works.
He however assured that TCN will connect the substation to the existing Single Circuit 330kV line from Benin to Osogbo which is not too far from the new Akure Substation, by turning it into the substation and out from the substation.
This he said, will be completed in five months enabling the energizing, testing, and commissioning of the project.
He lauded the cooperation of Osun, Ondo, and Edo state governors in helping TCN resolve several Right of Way issues, noting that the Minister of Power is collaborating with the Governors’ Forum to further resolve Right of Way issues across states, in order to hasten the delivery of power transmission projects across the country.
While inspecting the terminal points for the incoming transmission lines near the Akure Substation, Adewumi appealed to Ondo residents to safeguard power infrastructures against vandalism.
According to him, “everybody wants power but how can we have power when vandals keep bringing down power transmission lines?”
Copyright © 2022 Nigerian Tribune Provided by SyndiGate Media Inc. (Syndigate.info).