PHOTO
Dubai Electricity and Water Authority (DEWA) announced on Wednesday that it has completed 84.52 percent of the 829-megawatt (MW) Phase 4 of H-Station power plant in Al Aweer.
The 1.1-billion UAE dirham ($299.5 million) project is expected to be operational by the second quarter of 2022, DEWA said in a press statement.
It said the natural gas-fuelled power project will increase the H-Station's total capacity to 2,825 MW under climate conditions of up to 50 degrees Celsius.
Saeed Mohammed Al Tayer, MD & CEO of DEWA, said Phase 4 of H-Station will help DEWA meet the reserve margin criterion set for peak electricity demand in Dubai.
H-Station currently has a total capacity of 1,996 MW.
The DEWA statement said Phase 4 incorporates three Siemens gas turbines, natural gas compressors from Germany's MAN and natural gas treatment station from Dutch company Petrogas.
DEWA's current installed power generation capacity stands at 12,900 MW.
SDC Deal Number: 4214588158
(Writing by N Madhura; Editing by Anoop Menon)
Disclaimer: This article is provided for informational purposes only. The content does not provide tax, legal or investment advice or opinion regarding the suitability, value or profitability of any particular security, portfolio or investment strategy. Read our full disclaimer policy here.
© ZAWYA 2021