• EPC-plus-Finance Project with Japan’s ECA support
  • Completion ahead the scheduled for all substations

ELSEWEDY ELECTRIC S.A.E. (EGX: SWDY.CA), the leading Integrated Energy and Infrastructure Solution Provider in the Middle East and Africa, with Toyota Tsusho Corporation (TTC)[i], announces Iraqi Ministry of Electricity (MoE) completion for the EPC contract of four (4) gas insulated switchgear (GIS) substations, 400/132/11 kilovolt in Sothern Iraq.

In a ceremony witnessed by officials of the Government of Iraq today in Basra, His Excellency, Asaad Al-Eidani, the Governor of Basra with Ziyad Ali Fadel, the Director of the General Directorate of Electricity Transmission in the South Region joined the President and CEO of ELSEWEDY ELECTRIC, Ahmed Elsewedy, and TTC Project Manager, Yasuhiro Hidaka, to officially inaugurate Shat Alarab substation in Basra as the last substation connected to the Iraqi grid.

The ¥60 billion EPC-plus-Finance contract was signed on February 2018 under a buyer's credit agreement (export loan) between the Iraqi Ministry of Finance and The Japan Bank for International Cooperation (JBIC), with a co-financed portion by The Bank of Tokyo-Mitsubishi UFJ, Ltd. (lead arranger) and Sumitomo-Mitsui Banking Corporation under insurance cover by from Japan’s Nippon Export and Investment Insurance (NEXI).

The Contract included:

  • Maysan 400/132/11kV GIS substation in “Al-Amara Governorate”;
  • Al-Muthanna 400/132/11kV GIS substation in “Samawa Governorate”;
  • Shattra 400/132/11kV GIS substation in “Al-Nasiriya Governorate”;
  • Shatt Al Arab 400/132/11kV GIS substation in “Al-Basra Governorate”; and
  • 12 x 132/33kV Mobile GIS substations.

All GIS switchgears and high voltage transformers were manufactured by Toshiba Energy Systems & Solutions Corporation (Toshiba ESS) and equipment for 132/33kV mobile substations from Meidensha Corporation. The substations are expected to provide power for a combined total of approximately 1.3 million households.

ELSEWEDY ELECTRIC, which designed and built the 400/132/11kV GIS substations, qualified its engineers for testing and commissioning of GIS switchgear and transformers through an intensive training in Toshiba factories in Japan and India. Despite many challenges, ELSEWEDY ELECTRIC succeeded in completing each 400/132/11kV GIS substation ahead of the Contract schedule; approx. six months earlier than original schedule, where Maysan and Al-Muthanna were energized before Summer of 2020 then Shattra and Shatt Al Arab were energized before Summer of 2021.

ELSEWEDY ELECTRIC relied along the project on 1,200 Iraqi engineer and technicians supported by 180 Egyptian professionals, emphasizing on a business model for all its projects in Iraq leveraging on the Iraqi workforce while providing on-job development and training programmes.

“Completing five major challenging projects to the esteemed Iraqi Ministry of Electricity in five years while progress is ongoing in New Babil substation targeting 2022 spring reflects our strong commitment towards Iraq infrastructure development. Our products also are supplied to Iraq since 2005 and recently we committed to develop industrial park starting by factories of ELSEWEDY ELECTRIC serving the Iraqi market with further targets to export from Iraq to neighboring markets.”, commented Ahmed Elsewedy, President and CEO of ELSEWEDY ELECTRIC S.A.E.

ELSEWEDY ELECTRIC delivered AL DIWANIYA 500 megawatt power plant to the Iraqi Ministry of Electricity on 2015 as EPC main contractor. Currently, in a Consortium with TTC, ELSEWEDY ELECTRIC is building New Babil 400/132 kV substation, under Japan International Cooperation Agency (JICA) finance.

[i] For more information, the Press Release dated 30.03.2017 by Toyota Tsusho Corporation (TTC) at the following link: https://www.toyota-tsusho.com/english/press/detail/170330_003950.html

Send us your press releases to pressrelease.zawya@refinitiv.com

© Press Release 2021

Disclaimer: The contents of this press release was provided from an external third party provider. This website is not responsible for, and does not control, such external content. This content is provided on an “as is” and “as available” basis and has not been edited in any way. Neither this website nor our affiliates guarantee the accuracy of or endorse the views or opinions expressed in this press release.

The press release is provided for informational purposes only. The content does not provide tax, legal or investment advice or opinion regarding the suitability, value or profitability of any particular security, portfolio or investment strategy. Neither this website nor our affiliates shall be liable for any errors or inaccuracies in the content, or for any actions taken by you in reliance thereon. You expressly agree that your use of the information within this article is at your sole risk.

To the fullest extent permitted by applicable law, this website, its parent company, its subsidiaries, its affiliates and the respective shareholders, directors, officers, employees, agents, advertisers, content providers and licensors will not be liable (jointly or severally) to you for any direct, indirect, consequential, special, incidental, punitive or exemplary damages, including without limitation, lost profits, lost savings and lost revenues, whether in negligence, tort, contract or any other theory of liability, even if the parties have been advised of the possibility or could have foreseen any such damages.