- Measuring 225 metres in length, ‘The Link’ weighs 8,500 tonnes and will be suspended 105 metres in the air
Dubai, UAE: ALEC Engineering and Contracting L.L.C (ALEC), has commenced its two-week, seven-phase schedule to install ‘The Link’, a 8,500-tonne steel bridge, which will form the central feature of Ithra Dubai’s flagship, mixed-use, luxury development, One Za’abeel.
Comprised of two towers standing at 300 and 235 metres respectively, ‘The Link’ will become the world’s largest cantilevered Building, connecting the two buildings at a height of 105 metres, while providing panoramic views across the city.
As a process, the complexity of the engineering behind the lift is only equalled by the design of the cantilever itself. Comprised of seven steel modules, ‘The Link’ will be lifted in one piece, using a series of heavy-duty jacks capable of generating up to 6,600kN of force from 12 lifting points.
In the first phase, which was completed on Tuesday 18th, the concourse was elevated just 100mm over a 24-hour period – after monitoring its behaviour for nine hours, engineers removed the temporary steel fittings before cutting the shoes and lifting the structure a further metre over the period of seven hours. In the third phase, the team will install wind bracings to the side of the concourse in order to protect the lift from any adverse weather, while a 300-point survey will be conducted to ensure the integrity of the system. After a final phase of superficial improvements, the main lift is scheduled to take place on 31st August and include a 72 hours road closure as the giant concourse is elevated to its final position. Once in place, ‘The Link’ will be welded and tested, before the jacks are released and the load transferred to the towers.
Speaking on behalf of ALEC, Kez Taylor, chief executive officer, said: “It has been a great pleasure for ALEC to be able to work on such a unique and beautiful design. As a feat of engineering that pushes the boundaries of what’s possible, we look forward to seeing One Za’abeel take its place amongst the recognisable buildings that are now synonymous with Dubai’s reputation as a centre for architectural excellence and engineering excellence.”
With the final checks being completed by early September, One Za’abeel will eventually include retail, residential, hospitality and offices as part of its mixed-use status; giving its guests, tenants and visitors unmatched 360-degree views over the emirate.
-Ends-
© Press Release 2020
Disclaimer: The contents of this press release was provided from an external third party provider. This website is not responsible for, and does not control, such external content. This content is provided on an “as is” and “as available” basis and has not been edited in any way. Neither this website nor our affiliates guarantee the accuracy of or endorse the views or opinions expressed in this press release.
The press release is provided for informational purposes only. The content does not provide tax, legal or investment advice or opinion regarding the suitability, value or profitability of any particular security, portfolio or investment strategy. Neither this website nor our affiliates shall be liable for any errors or inaccuracies in the content, or for any actions taken by you in reliance thereon. You expressly agree that your use of the information within this article is at your sole risk.
To the fullest extent permitted by applicable law, this website, its parent company, its subsidiaries, its affiliates and the respective shareholders, directors, officers, employees, agents, advertisers, content providers and licensors will not be liable (jointly or severally) to you for any direct, indirect, consequential, special, incidental, punitive or exemplary damages, including without limitation, lost profits, lost savings and lost revenues, whether in negligence, tort, contract or any other theory of liability, even if the parties have been advised of the possibility or could have foreseen any such damages.