The Stage 2 load shedding being implemented from 11am on Wednesday, 2 February, until 5am on Monday morning is due to a shortage of generation capacity following breakdowns at two of Eskom's generating units. The breakdowns amount to at least 14,994MW of energy.
“Since the weekend, Eskom has utilised significant amounts of emergency generating reserves which have now been depleted and need to be replenished. Eskom will need this period of load shedding to replenish the emergency generation reserves.
“A unit each at Kusile and Kendal power stations tripped. Delays in returning units at Kusile, Tutuka, Duvha, Lethabo and Grootvlei have also contributed to the current supply constraints,” it said in a statement on Wednesday.
The power utility said it expects at least three generating units back in service by Wednesday afternoon.
Eskom has appealed to the public to reduce the usage of electricity and to switch off all non-essential items.
All rights reserved. © 2022. Bizcommunity.com Provided by SyndiGate Media Inc. (Syndigate.info).