Dubai Electricity and Water Authority said the Mohammed bin Rashid Al Maktoum (MBR) Solar Park, the largest single-site concentrated solar power project in the world, has reached its infrastructure completion phase with completion of the concrete base of the tower.

The concrete base contains about 1,300 tonnes of steel rebar and concrete, equivalent to 20 per cent of Paris’s Eiffel Tower.

Once built, the 260-m structure will be the tallest solar power tower in the world, said the statement from Dewa.

Saeed Mohammed Al Tayer, Managing Director and CEO of Dubai Electricity and Water Authority, Dewa, inspected the construction work of the Phase Four of the Solar Park, based on the independent power producer, IPP, model with a capacity of 950MW costing up to Dh15.78 billion.

Al Tayer was briefed on the progress of construction work by Abdul Hamid Al Muhaidib, the executive managing director of Noor Energy 1, a venture formed through a partnership between Dewa, Saudi Arabia’s Acwa Power and China’s Silk Road Fund to build the fourth phase of the park.

Al Muhaidib, confirming the completion of the concrete base, said the concrete placed weighs over 19,000 tonne, equivalent to the weight of 34 full A380s planes’ take-off weight with 555 passengers.

Al Muhaidib explained that 33 per cent of the engineering work has been completed for the project, which is proceeding according to plan.

This project is the largest single-site solar IPP project in the world that combines CSP and photovoltaic technology.

This phase will provide clean energy for 320,000 residences and will reduce 1.6 million tonnes of carbon emissions annually. The project, which will cover an area of 44 square kilometres, achieved several world records.

These include the world’s lowest CSP Levelised Cost of Electricity (LCoE), of $7.3 cents per kilowatt-hour and the lowest LCoE for photovoltaic technology of 2.4 US cents per kilowatt-hour.

Apart from being the tallest solar tower in the world, it will use 70,000 heliostats, and the largest thermal storage capacity of 15 hours, allowing for energy availability round the clock, said the statement from Dewa.

It will generate 5,000MW by 2030 with investments of up to Dh50 billion, it added.

According to Dewa, the 13MW photovoltaic first phase became operational in 2013. The 200MW photovoltaic second phase of the solar park was launched in March 2017 while the 200MW first stage of the 800MW photovoltaic third phase became operational in May 2018.

The third phase will be completed in 2020, it added.-TradeArabia News Service

Copyright 2019 Al Hilal Publishing and Marketing Group Provided by SyndiGate Media Inc. (Syndigate.info).

Disclaimer: The content of this article is syndicated or provided to this website from an external third party provider. We are not responsible for, and do not control, such external websites, entities, applications or media publishers. The body of the text is provided on an “as is” and “as available” basis and has not been edited in any way. Neither we nor our affiliates guarantee the accuracy of or endorse the views or opinions expressed in this article. Read our full disclaimer policy here.